The DataGrid Project

. . . 

 

QAG Actions List

Previous ended actions                New proposed actions are:
Date in Who Subject Deadline/status
1 27/08/02 QARs Monitor Test plans Permanent task
25 10/10/02 QAR6

Anomalies evolution (Quality Indicators)-. These indicators should be produced monthly by WP6 (Automated queries to Bugzilla).

It will be useful to get too the percentage of anomalies resolution time in each classes of time resolution range (low, medium, high).

Those indicators will be produced monthly, but it should be possible to get them on demand.

Done

 

Currently Sophie will produce them on demand and will evaluate the automatic script

29 10/10/02 QAR2

A WP2/WP3 proposal for web services could be found at:http://edms.cern.ch/document/364409

Action postponed to EGEE
30 23/01/03 QARs

Dev Guide- update:

·        Compiler version. Yannick should give some examples and specifies that it is not the only way to use it.

·          Cron job (Diana)

·           Unit.d location (German)

·          RFC 2606 (Abdeslem)

Permanent task
31 23/01/03 QAR6

A first draft of Bugzilla bug’s report procedure has been provided and agreed: https://edms.cern.ch/document/386113.

Sophie will implement the new features (notification to ITeam member, notification to the originator)

Done
32 06/03/03 QAR1

Quality indicators specifications (QoS): A first draft has been provided by QAR1: https://edms.cern.ch/document/386039


The final implementation plan will be delivered by David.

Gabriel will contact CrossGrid in order to see with them if they can monitor the RB. See implementation at: http://193.136.91.237/php/showrbstats.php?db=nikheflbserver

Done

 

done: but not implemented

done

33 06/03/03 QARs Make sure all EDG documentation is available in CVS+EDMS Permanent task
34 22/06/03 QARs

Release procedure & release checklist:

A release procedure checklist has been provided by Erwin & Gabriel (05/06/2003): https://edms.cern.ch/document/387659

The quality group member of each WP monitors the progress and reports to the WP mgr. Before an integration slot starts, the QAR informs the QAG about the requirements adherence through the release checklist.

It has to be delivered on the day the integration slot for your WP starts (see the TB3 release plan: https://edms.cern.ch/document/382573)

We received the QA checklist from:

VOMS- https://edms.cern.ch/document/404428

LCMAPS- https://edms.cern.ch/document/404431

RLS-http://cern.ch/edg-wp2/release2.1/index.html#quality

We received a good feedback concerning the use of Checklist as a good tool for QA improvement

done
35 24/07/03 Gabriel, Sophie, David

Preparation of QAG presentation at Heidelberg:

QAG report:

https://edms.cern.ch/document/405143

Performance indicators:
https://edms.cern.ch/document/386039

done